We are so excited to be adding a branch at 24th and Industrial. We thought you might like to check in every now and then to see what progress has been made. October 20th The texturing is being done on the South side. The outdoor light fixtures are installed. Work is fast and furious on the East side of the building. Our new home is looking good! October 12th The front parking lot is almost done! October 6th It's time to pour more concrete for the front parking lot. Scafolding is put in place so that texturing can begin. The ATM Machine arrives! AND the carpet arrives! October 1st The front parking lot is taking shape! Inside, countertops were delivered. September 29th A section of the front parking lot is ready for concrete! September 25th The concrete for the Drive Thru lanes are poured. The inside work continues. . .
September 18th September 17th
The interior Drive Up tubes have been installed. The second floor has been painted. September 14th The lighting on the second floor is installed. September 11th The ceiling structure is going up. And work on the Drive Up continues . . . August 31st August 29th The interior paint first coat is almost done. August 28th Interior wiring continues.
August 25th Interior: August 21st August 13th - Interior August 13th - Exterior August 5th July 27th July 24th - A small portion of the outside gets the brick! Manager Miller looks on as the bricking continues.
July 22nd - Work on the 2nd floor is going strong! July 21st - Windows are going in! July 16th - Work begins on the Drive Thru lanes! July 9th and 10th - The Roofing Begins!!! Simon, Becky, Judy and Joni check out the drive thru! July 1 - The interior framing is coming along! June 30th - Assistant Manager Josh Hubler (L) and Manager Angie Miller discuss the branch interior. June 26 - The building continues - despite record heat. June 24/25 - The water line is put in. June 23rd
June 22nd June 18th June 16 - The Branch is taking shape! June 15th June 12th June 4th and 5th - Roofing Begins!!!!
June 3rd - 2nd Floor Framing begins! June 2nd - Support beams for the second floor are lifted into place and secured. May 28th - Work on the elevator shaft and the indoor framing begins.
May 21 & 22 - The first floor ceiling is readied and poured. May 15th - Operations Manager, Joni Vaughn and Assistant Manager, Josh Hubler see the inside of the branch for the first time.
More views of the inside of the branch. May 7th - Ceiling beams are installed.
May 6, 2009 - The Vault Arrives! May 5, 2009 - The concrete walls are poured.
April 29, 2009 - The walls go up! In our continuing effort to build Green, our branch is being built with Insulated Concrete Forms (ICF's). Using ICF's will help us reduce our energy consumption for heating and cooling by 30-50%. It also can generate as little as 1% construction waste. This greatly reduces land filling which produces methane emissions. In addition, using this recycled material reduces the number of trees that need to be cut down.
April 25, 2009 - The first floor concrete is poured.
April 15, 2009 - The crew is putting in the 1st floor supports. February 4, 2009 The Groundbreaking. The groundbreaking ceremony was held on October 31, 2008. The video of the groundbreaking is at the top of the page. Click Here to view the plans and more groundbreaking photos. Building Progress: CU Branch Groundbreaking - October 31, 2008
|